MISSION OF COAL INDIA - To produce and market the planned quantity of coal and coal products efficiently and economically in an eco-friendly manner with due regard to safety, quality and conservation. VISION OF COAL INDIA - To emerge as a global player in the primary energy sector committed to provide energy security to the country by attaining environmentally & socially sustainable growth through best practices from mine to market.

POPULATION OF EQUIPMENT (HEMM)

Population of Equipment as on 31st March, 2019 compared to 31st March, 2018:

Equipment

No. of Equipment as on

31.03.2019

31.03.2018

Dragline

1

1

Dumper

262

252

Dozer

84

82

Shovel

57

54

Drill

52

48

Percentage availability and utilisation of each type of equipment against CMPDIL norms during the year 2018-19 compared to previous year is as follows:

Equipment

Percentage Availability

Percentage Utilisation

CMPDIL Norms

2018-19

2017-18

Variation over last year

CMPDIL Norms

2018-19

2017-18

Variation over last year

Dragline

85

89.32

74.08

15.24

73

82.21

57.45

24.76

Dumper

67

80.26

83.56

-3.30

50

33.09

31.83

1.26

Dozer

70

75.20

74.47

0.73

45

21.62

23.53

-1.91

Shovel

80

80.30

79.16

1.14

58

46.48

47.00

-0.52

Drill

78

85.08

84.87

0.21

40

20.36

20.52

-0.16

Utilisation of equipment suffered mainly because:

Project

Constraints

Rajmahal

1. Due to concentrated working place, crowding of equipments and land acquisition problem.

2. Poor reliability of 170T dumpers: 7 nos. of 170T dumpers are grounded as on 4th April, 2019.

3. Delay in procurement of 190T dumpers and 20 Cum shovel by CIL.

Sonepur Bazari

1. Availability of new 10 Cum shovel is adversely affected due to non availability of float sub-assemblies with OEM’s store in India.

2. Restricted dumping area.

Shankarpur

Working over underground, fiery face and difficult mining conditions.

Khottadih

1. Land acquisition problem due to resistance by villagers.

2. Operation of HEMM in a confined strike length of mine-less working area due to land acquisition problem.

Mohanpur

Land acquisition problem and manpower problem at operational as well as maintenance departments.

Jambad

Land acquisition problem due to non-shifting of local inhabitants.

Rajpura

Restricted blasting due to nearness of villages.

Baramuri

Limited working space, narrow haul road for only one dumper to ply.

New/Replacement equipment provided to OCPs in 2018-19 is as under:

Equipment

Nos.

Project

Dumper

14

Rajmahal-6, North Searsole-1, Chitra-6 and Shankarpur-1.

Dozer

6

North Searsole-1, Chitra-2, Baramuri-1, Begunia-1 and Bonjemehari-1.

Shovel

3

Sonepur Bazari-1, North Searsole-1 and Chitra-1.

Drill

4

Mohanpur-1, Chitra-1, Shankarpur-1 and Dabor-1.

 

001 002 003 004



DISCLAIMER : Information on this site is believed to be accurate but ECL disclaims any liability for any errors or omissions that may occur from time to time.

Copyright 2019 EASTERN COALFIELDS LIMITED,
Sanctoria, Post: Dishergarh, Dist.: West Bardhaman, W.B., PIN - 713 333 Tel: 0341-2520052-53, 2520414 Fax: 0341-2523574 Gram: EASTCOAL